Dept. of Trans. PROGRESS Serial No. Contract No. 06-298-07-32 07-4K3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 23% 07-LA-101-33.7/33.7 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-06 HIGHLAND CONSTRUCTION INC 133 N PIXLEY STREET ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 295,446.00 295,446.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 295,446.00 295,446.00 5. Mobilization 43,400.00 43,400.00 6. Total Work Completed 338,846.00 7. Deductions 8. a.Contract Retentions -14,772.30 -14,772.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 324,073.70 324,073.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 324,073.70