Dept. of Trans. PROGRESS Serial No. Contract No. 06-360-13-43 07-4K6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 26% 07-LA-60-11.2/11.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-06 ODONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 371,188.50 258,392.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 371,188.50 258,392.00 5. Mobilization 49,400.00 10,400.00 6. Total Work Completed 420,588.50 7. Deductions 8. a.Contract Retentions -18,559.43 -7,279.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 402,029.07 261,512.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 261,512.22