Dept. of Trans. PROGRESS Serial No. Contract No. 07-206-09-07 07-4K6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-60-11.2/11.2 Federal Project: NONE Progress payment No. 10 Payment period ending: 07-20-07 ODONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 02270 Total Estimate This Estimate 1. Contract Itms Without Mobil. 759,007.21 3,330.00 2.a. Extra Work 32,197.13 2,239.86 b. Adjustment Comp. 17,893.71 0.00 3. Materials on Hand 4. Earned Subject to Retention 809,098.05 5,569.86 5. Mobilization 52,000.00 0.00 6. Total Work Completed 861,098.05 7. Deductions 8. a.Contract Retentions -40,454.90 -278.49 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 820,643.15 5,291.37 10. Reduction Amt to Escrow 11. Payment to Escrow 40,170.00 12. Net Pymt. this Estimate 5,291.37