Dept. of Trans. PROGRESS Serial No. Contract No. 05-066-15-15 07-4K7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 100% 07-VEN-33-5.6/45.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 03-06-05 SUMMER CONSTRUCTION, INC. 1184 NORTH OAK AVE. FILLMORE, CA 93015 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,100.00 0.00 2.a. Extra Work 931.50 931.50 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,031.50 931.50 5. Mobilization 6. Total Work Completed 12,031.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,031.50 931.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 931.50