Dept. of Trans. PROGRESS Serial No. Contract No. 06-066-10-14 07-4L2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 100% 07-VEN-150-22.5/23.5 Federal Project: NONE Progress payment No. 02 Payment period ending: 02-06-06 C.A. RASMUSSEN, INC. 2360 SHASTA WAY SIMI VALLEY, CA 93065 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 425,098.76 205,063.99 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 425,098.76 205,063.99 5. Mobilization 6. Total Work Completed 425,098.76 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 425,098.76 205,063.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 205,063.99