Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-088-09-40 07-4L3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-VEN-23-1.9/1.9 Federal Project: NONE Progress payment No. 04 Payment period ending: 02-23-07 T D S ENGINEERING 2899 AGOURA ROAD SUITE 171 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 201,476.00 0.00 2.a. Extra Work 7,575.45 7,575.45 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 209,051.45 7,575.45 5. Mobilization 20,000.00 0.00 6. Total Work Completed 229,051.45 7. Deductions 8. a.Contract Retentions -10,073.80 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 10,073.80 10,073.80 9. Total pay to Contractor 229,051.45 17,649.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,649.25