Dept. of Trans. PROGRESS Serial No. Contract No. 09-267-09-18 07-4L4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 100% 07-VEN-150-20.5/31.0 Federal Project: ACST-4130(4) P-4130(4) Progress payment No. 09 Payment period ending: 09-20-09 RSB GROUP INC 22600 G LAMBERT ST SUITE 1405 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 772,029.50 21,075.00 2.a. Extra Work 168,583.03 47,378.91 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 940,612.53 68,453.91 5. Mobilization 117,000.00 0.00 6. Total Work Completed 1,057,612.53 7. Deductions -33,085.50 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,024,527.03 68,453.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,453.91