Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-026-13-14 07-4L5004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-14-39.8/R68.0 Federal Project: NONE Progress payment No. 06 Payment period ending: 10-21-08 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 650,303.10 0.00 2.a. Extra Work 79,606.15 32,155.08 b. Adjustment Comp. 3,862.88 3,862.88 3. Materials on Hand 4. Earned Subject to Retention 733,772.13 36,017.96 5. Mobilization 35,000.00 0.00 6. Total Work Completed 768,772.13 7. Deductions 8. a.Contract Retentions -31,227.02 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 31,227.02 0.00 9. Total pay to Contractor 768,772.13 36,017.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,017.96