Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-15-51 07-4L5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 26% 07-LA-57-R0.9/R11.6 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-20-07 PAVE TECH INC 735 LAGUNA DR CARLSBAD CA 92008 Escrow No. 02308 Total Estimate This Estimate 1. Contract Itms Without Mobil. 104,513.20 93,413.20 2.a. Extra Work 750.00 750.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 105,263.20 94,163.20 5. Mobilization 90,140.50 90,140.50 6. Total Work Completed 195,403.70 7. Deductions -2,500.00 0.00 8. a.Contract Retentions -10,526.32 -9,416.32 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 182,377.38 174,887.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 174,887.38