Dept. of Trans. PROGRESS Serial No. Contract No. 08-023-10-45 07-4L5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 65% 07-LA-57-R0.9/R11.6 Federal Project: NONE Progress payment No. 08 Payment period ending: 01-20-08 PAVE TECH INC 735 LAGUNA DR CARLSBAD CA 92008 Escrow No. 02308 Total Estimate This Estimate 1. Contract Itms Without Mobil. 754,042.02 228,803.64 2.a. Extra Work 31,334.91 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 785,376.93 228,803.64 5. Mobilization 171,266.95 0.00 6. Total Work Completed 956,643.88 7. Deductions -2,500.00 0.00 8. a.Contract Retentions -43,890.58 0.00 b. Unsatisfactory Prog. -19,238.78 -11,440.18 c. Reduction after 95% Comp. 9. Total pay to Contractor 891,014.52 217,363.46 10. Reduction Amt to Escrow 11. Payment to Escrow 43,890.00 12. Net Pymt. this Estimate 217,363.46