Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-15-13 07-4L5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 13% 07-VEN-150-28.6/28.7 Federal Project: ACST-4138(4) P-4138(4) Progress payment No. 07 Payment period ending: 09-20-11 C A RASMUSSEN INC 28548 LIVINGSTON AVENUE VALENCIA CA 91355 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 291,430.00 6,140.00 2.a. Extra Work 30,657.06 20,404.05 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 322,087.06 26,544.05 5. Mobilization 173,250.00 0.00 6. Total Work Completed 495,337.06 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 495,337.06 26,544.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,544.05