Dept. of Trans. PROGRESS Serial No. Contract No. 08-267-15-08 07-4L7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 73% 07-LA-105-R0.5/R0.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 09-20-08 RSB GROUP INC 22600-G LAMBERT STREET #1405 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 178,687.30 104,479.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -16,448.70 4. Earned Subject to Retention 178,687.30 88,030.60 5. Mobilization 95,000.00 20,000.00 6. Total Work Completed 273,687.30 7. Deductions -56,635.72 -16,739.10 8. a.Contract Retentions -8,934.37 -973.47 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 208,117.21 90,318.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 90,318.03