Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-058-08-57 07-4L7504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-VEN-126-29.8/32.7 Federal Project: NONE Progress payment No. 04 Payment period ending: 02-08-07 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 535,750.80 37,901.00 2.a. Extra Work 5,978.39 5,978.39 b. Adjustment Comp. -30,875.58 -30,875.58 3. Materials on Hand 4. Earned Subject to Retention 510,853.61 13,003.81 5. Mobilization 45,000.00 0.00 6. Total Work Completed 555,853.61 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -24,892.49 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 24,892.49 24,892.49 9. Total pay to Contractor 545,853.61 27,896.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,896.30