Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-078-08-32 07-4L7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-1-19.4/32.0 Federal Project: OTS Progress payment No. 06 Payment period ending: 02-26-09 FREEWAY ELECTRIC P O BOX 7745 RIVERSIDE CA 925137745 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 186,247.60 2,500.00 2.a. Extra Work 5,632.07 2,081.10 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 191,879.67 4,581.10 5. Mobilization 12,652.40 0.00 6. Total Work Completed 204,532.07 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 204,532.07 4,581.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,581.10