Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-15-51 07-4L8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-110-13.7/19.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-07 HIGHLAND CONSTRUCTION INC 133 N PIXLEY STREET ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 316,670.50 165,794.50 2.a. Extra Work 1,408.35 1,408.35 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 318,078.85 167,202.85 5. Mobilization 30,000.00 1,500.00 6. Total Work Completed 348,078.85 7. Deductions 8. a.Contract Retentions -15,903.94 -8,360.14 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 332,174.91 160,342.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 160,342.71