Dept. of Trans. PROGRESS Serial No. Contract No. 07-206-11-08 07-4L8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 94% 07-LA-110-20.6/20.7 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-20-07 COAST CONSTRUCTION INC 4460 REDWOOD HIGHWAY SUITE 16 SAN RAFAEL CA 94903 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 102,522.00 28,150.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 102,522.00 28,150.00 5. Mobilization 14,000.00 700.00 6. Total Work Completed 116,522.00 7. Deductions -4,000.00 0.00 8. a.Contract Retentions -5,126.10 -1,355.02 b. Unsatisfactory Prog. 0.00 2,481.75 c. Reduction after 95% Comp. 9. Total pay to Contractor 107,395.90 29,976.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,976.73