Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-030-16-21 07-4L8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-110-20.6/20.7 Federal Project: NONE Progress payment No. 09 Payment period ending: 12-28-07 COAST CONSTRUCTION INC 4460 REDWOOD HIGHWAY SUITE 16 SAN RAFAEL CA 94903 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 184,722.00 21,380.00 2.a. Extra Work 24,144.16 24,144.16 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 208,866.16 45,524.16 5. Mobilization 14,000.00 0.00 6. Total Work Completed 222,866.16 7. Deductions 0.00 4,000.00 8. a.Contract Retentions -8,167.10 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 8,167.10 8,167.10 9. Total pay to Contractor 222,866.16 57,691.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 57,691.26