Dept. of Trans. PROGRESS Serial No. Contract No. 08-053-09-44 07-4L9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 46% 07-LA-101-1.3/31.9 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-20-08 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008 Escrow No. 02330 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,072.75 253,972.70 2.a. Extra Work 8,125.47 7,414.34 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 629,198.22 261,387.04 5. Mobilization 122,000.00 6,100.00 6. Total Work Completed 751,198.22 7. Deductions 8. a.Contract Retentions -31,459.91 -8,516.99 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 719,738.31 258,970.05 10. Reduction Amt to Escrow 11. Payment to Escrow 31,450.00 12. Net Pymt. this Estimate 258,970.05