Dept. of Trans. PROGRESS Serial No. Contract No. 08-113-10-01 07-4L9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 43% 07-LA-101-1.3/31.9 Federal Project: NONE Progress payment No. 07 Payment period ending: 04-20-08 PAVE TECH INC 735 LAGUNA DRIVE CARLSBAD CA 92008 Escrow No. 02330 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,072.75 0.00 2.a. Extra Work 12,365.93 3,274.79 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 633,438.68 3,274.79 5. Mobilization 122,000.00 0.00 6. Total Work Completed 755,438.68 7. Deductions 8. a.Contract Retentions -31,671.93 -163.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 723,766.75 3,111.05 10. Reduction Amt to Escrow 11. Payment to Escrow 31,450.00 12. Net Pymt. this Estimate 3,111.05