Dept. of Trans. FINAL Serial No. Contract No. 09-258-14-55 07-4L9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-105-R8.4/R15.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-28-09 J MC LOUGHLIN ENGINEERING CO INC 10641 FULTON COURT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 146,986.00 0.00 2.a. Extra Work 954.52 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 147,940.52 0.00 5. Mobilization 15,000.00 0.00 6. Total Work Completed 162,940.52 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 162,940.52 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00