Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-209-13-19 07-4L9904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-210-R32.8/R46.3 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-10-09 CAROLINO CONSTRUCTION CORPORATION 3035 EAST 8TH STREET NATIONAL CITY CA 91950 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 480,137.03 0.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 480,137.03 0.00 5. Mobilization 31,836.00 0.00 6. Total Work Completed 511,973.03 7. Deductions -22,500.00 27,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 489,473.03 27,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,000.00