Dept. of Trans. PROGRESS Serial No. Contract No. 09-147-10-44 07-4S1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 77% 07-LA-10-18.5/21.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 05-20-09 BENA COMPANY 2785 PACIFIC COAST HWY NO322E TORRANCE CA 90505 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,638.00 41,508.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 42,638.00 41,508.00 5. Mobilization 4,750.00 4,750.00 6. Total Work Completed 47,388.00 7. Deductions -500.00 -300.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 46,888.00 45,958.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,958.00