Dept. of Trans. PROGRESS Serial No. Contract No. 09-023-07-53 07-4S2704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 50% 07-LA-138-60.0/60.4 Federal Project: NONE Progress payment No. 02 Payment period ending: 01-20-09 CALIFORNIA ENGINEERING AND CONTRACTING INC 16027 BROOKHURST ST SUITE G24 FOUNTAIN VALLEY CA 92708 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 127,145.00 93,950.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 127,145.00 93,950.00 5. Mobilization 1,500.00 375.00 6. Total Work Completed 128,645.00 7. Deductions 8. a.Contract Retentions -6,357.25 -3,037.75 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 122,287.75 91,287.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 91,287.25