Dept. of Trans. PROGRESS Serial No. Contract No. 09-268-11-11 07-4S3704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 35% 07-LA-1-47.5/62.2 Federal Project: OTS Progress payment No. 03 Payment period ending: 09-20-09 DREAMBUILDER 1361 E GARTEN DRIVE PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,175.74 0.00 2.a. Extra Work 73,958.38 58,390.46 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 127,134.12 58,390.46 5. Mobilization 9,186.50 0.00 6. Total Work Completed 136,320.62 7. Deductions -13,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 123,320.62 58,390.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,390.46