Dept. of Trans. PROGRESS Serial No. Contract No. 09-023-07-53 07-4S4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 98% 07-LA-405-0.3/2.8 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-09 ODONNELL CONSTRUCTION INC 559 W COVINA BOULEVARD SAN DIMAS CA 917732911 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 367,639.75 179,814.75 2.a. Extra Work 2,920.70 2,920.70 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 370,560.45 182,735.45 5. Mobilization 24,000.00 0.00 6. Total Work Completed 394,560.45 7. Deductions 8. a.Contract Retentions -18,528.02 -9,136.77 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 376,032.43 173,598.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,598.68