Dept. of Trans. PROGRESS Serial No. Contract No. 11-236-14-49 07-4S8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 42% 07-LA-110-24.0/27.0 Federal Project: NHX-037(152) Progress payment No. 02 Payment period ending: 08-20-11 CROWN FENCE CO 230 RIVER ROAD CORONA CA 92880 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,847.50 1,847.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 42,740.64 0.00 4. Earned Subject to Retention 44,588.14 1,847.50 5. Mobilization 1,875.00 0.00 6. Total Work Completed 3,722.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 46,463.14 1,847.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,847.50