Dept. of Trans. PROGRESS Serial No. Contract No. 10-265-16-25 07-4S8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 40% 07-VEN-23-3.5/8.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 09-20-10 CLEAN CUT LANDSCAPE 8406 N ARMSTRONG CLOVIS CA 93619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 161,513.25 25,319.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 161,513.25 25,319.00 5. Mobilization 10,000.00 0.00 6. Total Work Completed 171,513.25 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 171,513.25 25,319.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,319.00