Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-173-11-24 07-4S9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-5707 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-05-11 DREAMBUILDER 1361 E GARTEN DRIVE PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 425,585.45 0.00 2.a. Extra Work 26,621.12 25,708.48 b. Adjustment Comp. 25,765.52 20,765.52 3. Materials on Hand 4. Earned Subject to Retention 477,972.09 46,474.00 5. Mobilization 6. Total Work Completed 477,972.09 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 477,972.09 46,474.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,474.00