Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-302-14-18 07-4T0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-101-2.6/2.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-21-09 T D S ENGINEERING 1014 S WESTLAKE BLVD STE 1413 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 144,229.00 5,560.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 144,229.00 5,560.00 5. Mobilization 1,000.00 0.00 6. Total Work Completed 145,229.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 145,229.00 5,560.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,560.00