Dept. of Trans. PROGRESS Serial No. Contract No. 11-055-15-04 07-4T0604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 373% 07-LA-1-38.7/56.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-20-11 TRAFFIC DEVELOPMENT SERVICES INC 4215 TIERRA REJADA RD STE 184 MOORPARK CA 93021 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 456,697.00 0.00 2.a. Extra Work 3,634.93 3,634.93 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 460,331.93 3,634.93 5. Mobilization 6. Total Work Completed 460,331.93 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 460,331.93 3,634.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,634.93