Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-172-14-35 07-4T1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-105-R13.0/R13.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-10-10 O DONNELL CONSTRUCTION INC 559 WEST COVINA BOULEVARD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 283,602.00 0.00 2.a. Extra Work b. Adjustment Comp. 618.22 618.22 3. Materials on Hand 4. Earned Subject to Retention 284,220.22 618.22 5. Mobilization 23,000.00 0.00 6. Total Work Completed 307,220.22 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 307,220.22 618.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 618.22