Dept. of Trans. PROGRESS Serial No. Contract No. 11-025-14-26 07-4T1904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 68% 07-LA-1-1.9/4.1 Federal Project: NONE Progress payment No. 06 Payment period ending: 01-20-11 LINCOLN PACIFIC BUILDERS INC 4501 LITTLEJOHN STREET BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 166,321.43 79,310.00 2.a. Extra Work 427.78 427.78 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 166,749.21 79,737.78 5. Mobilization 5,000.00 250.00 6. Total Work Completed 171,749.21 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 171,749.21 79,987.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 79,987.78