Dept. of Trans. PROGRESS Serial No. Contract No. 13-056-13-00 07-4T4204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 65% 07-LA-1-32.6/32.6 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-20-13 SULLY-MILLER CONTRACTING COMPANY 135 S STATE COLLEGE STE 400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 143,333.98 18,683.28 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 143,333.98 18,683.28 5. Mobilization 10,000.00 0.00 6. Total Work Completed 153,333.98 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 153,333.98 18,683.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,683.28