Dept. of Trans. PROGRESS Serial No. Contract No. 15-026-10-04 07-4T6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 82% 07-LA-105-14.1/14.6 Federal Project: NONE Progress payment No. 06 Payment period ending: 01-20-15 HYPA ENGINEERING INC 4623 NORWICH AVE SHERMAN OAKS CA 91403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 493,500.00 99,250.00 2.a. Extra Work 31,856.96 20,188.28 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 525,356.96 119,438.28 5. Mobilization 6. Total Work Completed 525,356.96 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 525,356.96 119,438.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 119,438.28