Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-14-54 07-4T6404 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 88% Location: Federal Project: 07-LA-105-14.1/14.6 NONE Progress payment No. 008 Payment period ending: 03-20-15 HYPA ENGINEERING INC 4623 NORWICH AVE SHERMAN OAKS CA 91403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 532,250.00 0.00 2. a. Extra Work 44,015.50 8,449.95 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 576,265.50 8,449.95 5. Mobilization 6. Total Work Completed 576,265.50 7. Deductions -8,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 568,265.50 8,449.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,449.95