Dept. of Trans. PROGRESS Serial No. Contract No. 15-113-09-31 07-4T6404 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 91% Location: Federal Project: 07-LA-105-14.1/14.6 NONE Progress payment No. 009 Payment period ending: 04-20-15 HYPA ENGINEERING INC 4623 NORWICH AVE SHERMAN OAKS CA 91403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 571,750.00 39,500.00 2. a. Extra Work 70,036.16 26,020.66 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 641,786.16 65,520.66 5. Mobilization 6. Total Work Completed 641,786.16 7. Deductions -10,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 631,786.16 63,520.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,520.66