Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-15-06 07-4T6804 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 77% Location: Federal Project: 07-LA-105-0.9/4.9 NHPI-105-3(4) Progress payment No. 006 Payment period ending: 03-20-15 SMART TECH GROUP INC 3972 BARRANCA PARKWAY # J283 IRVINE CA 92606 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 384,869.74 67,900.00 2. a. Extra Work 13,449.07 13,449.07 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 398,318.81 81,349.07 5. Mobilization 24,000.00 0.00 6. Total Work Completed 422,318.81 7. Deductions -2,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 420,318.81 82,349.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,349.07