Dept. of Trans. FINAL Serial No. Contract No. 17-219-09-14 07-4T7104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-66-2.9/2.9 HSST-PG S066-009E Progress payment No. 009 Payment period ending: 05-09-17 FERREIRA CONSTRUCTION CO INC 15188 VISTA DEL RIO AVE CHINO CA 91710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 368,041.00 0.00 2. a. Extra Work b. Adustment Comp. 18,205.20 1,032.02 3. Materials on Hand 4. Earned Subject to Retention 386,246.20 1,032.02 5. Mobilization 15,600.00 0.00 6. Total Work Completed 401,846.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 401,846.20 1,032.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,032.02