Dept. of Trans. PROGRESS Serial No. Contract No. 16-357-16-34 07-4T7304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 85% Location: Federal Project: 07-LA-405-41.6/41.6 HSNH-405-3(24) Progress payment No. 009 Payment period ending: 12-20-16 HIGHLAND CONSTRUCTION INC 133 N PIXLEY ST ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 720,032.00 0.00 2. a. Extra Work 90,512.61 18,734.68 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 810,544.61 18,734.68 5. Mobilization 48,250.00 0.00 6. Total Work Completed 858,794.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 858,794.61 18,734.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,734.68