Dept. of Trans. PROGRESS Serial No. Contract No. 15-324-10-16 07-4T7404 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 100% Location: Federal Project: 07-LA-134-R10.8/R11.5 NHP-P134(38) Progress payment No. 002 Payment period ending: 11-20-15 ODONNELL CONSTRUCTION, INC. 559 W COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 150,510.00 77,642.40 2. a. Extra Work 10,341.30 7,341.30 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 160,851.30 84,983.70 5. Mobilization 6. Total Work Completed 160,851.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -8,498.37 -8,498.37 c. Reduction after 95% Comp. 9. Total pay to Contractor 152,352.93 76,485.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 76,485.33