Dept. of Trans. PROGRESS Serial No. Contract No. 18-023-18-03 07-4T8204 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 100% Location: Federal Project: 07-VEN-150-8.7/29.8 STHG-P150(27) Progress payment No. 003 Payment period ending: 01-20-18 C & W CONSTRUCTION SPECIALTIES INC 2419 PALMA DRIVE VENTURA CA 93003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 256,764.23 58,020.70 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 256,764.23 58,020.70 5. Mobilization 2,821.00 0.00 6. Total Work Completed 259,585.23 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 239,585.23 38,020.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,020.70