Dept. of Trans. PROGRESS Serial No. Contract No. 19-234-11-42 07-4T8604 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 74% Location: Federal Project: 07-VEN-118-12.6/13.7 NONE Progress payment No. 005 Payment period ending: 08-20-19 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 329,238.59 17,723.65 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 329,238.59 17,723.65 5. Mobilization 17,000.00 0.00 6. Total Work Completed 346,238.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 346,238.59 17,723.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,723.65