Dept. of Trans. PROGRESS Serial No. Contract No. 19-053-14-05 07-4T8704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 97% Location: Federal Project: 07-LA-405-24.3/24.3 SIMG-405-3(36) Progress payment No. 006 Payment period ending: 02-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 267,425.90 0.00 2. a. Extra Work 13,502.75 4,897.41 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 280,928.65 4,897.41 5. Mobilization 25,000.00 0.00 6. Total Work Completed 305,928.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 305,928.65 4,897.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,897.41