Dept. of Trans. PROGRESS Serial No. Contract No. 21-112-11-49 07-4U0504 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 7% Location: Federal Project: 07-LA-405-41.3/41.3 NONE Progress payment No. 004 Payment period ending: 04-20-21 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 379,715.46 6,531.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 379,715.46 6,531.25 5. Mobilization 22,000.00 0.00 6. Total Work Completed 401,715.46 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 401,715.46 6,531.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,531.25