Dept. of Trans. PROGRESS Serial No. Contract No. 23-204-15-29 07-4U1604 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 36% Location: Federal Project: 07-LA-210-R19.6/R20.3 NONE Progress payment No. 009 Payment period ending: 07-20-23 MARINA LANDSCAPE INC. 3707 W GARDEN GROVE BLVD ORANGE CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 700,904.00 102,711.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 700,904.00 102,711.00 5. Mobilization 30,000.00 0.00 6. Total Work Completed 730,904.00 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 728,904.00 102,711.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,711.00