Dept. of Trans. PROGRESS Serial No. Contract No. 23-170-20-26 07-4V0204 PROGRESS PAYMENT VOUCHER %complete: %time: 27% 60% Location: Federal Project: 07-LA-213-2.2/2.2 NONE Progress payment No. 003 Payment period ending: 06-20-23 CROSSTOWN ELECTRICAL & DATA INC 5454 DIAZ ST IRWINDALE CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 115,090.70 73,922.62 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 115,090.70 73,922.62 5. Mobilization 19,000.00 9,000.00 6. Total Work Completed 134,090.70 7. Deductions -30,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 104,090.70 72,922.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 72,922.62