Dept. of Trans. PROGRESS Serial No. Contract No. 22-355-12-14 07-4V0304 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 0% Location: Federal Project: 07-LA-90-1.8/1.8 NONE Progress payment No. 002 Payment period ending: 12-20-22 CROSSTOWN ELECTRICAL & DATA INC 5454 DIAZ ST IRWINDALE CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 95,572.72 27,300.39 4. Earned Subject to Retention 95,572.72 27,300.39 5. Mobilization 18,750.00 6,250.00 6. Total Work Completed 18,750.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 114,322.72 33,550.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,550.39