Dept. of Trans. PROGRESS Serial No. Contract No. 24-204-21-37 07-4V0304 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 83% Location: Federal Project: 07-LA-90-1.8/1.8 NONE Progress payment No. 006 Payment period ending: 07-20-24 CROSSTOWN ELECTRICAL & DATA INC 5454 DIAZ ST IRWINDALE CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 368,563.89 135,286.33 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 27,300.39 0.00 4. Earned Subject to Retention 395,864.28 135,286.33 5. Mobilization 25,000.00 1,250.00 6. Total Work Completed 393,563.89 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 420,864.28 136,536.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,536.33