Dept. of Trans. PROGRESS Serial No. Contract No. 21-326-11-44 07-4V1004 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 24% Location: Federal Project: 07-LA-91-R10.0/R10.3 AVNH-P091(150) Progress payment No. 002 Payment period ending: 11-20-21 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 203,982.00 55,230.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 203,982.00 55,230.00 5. Mobilization 64,600.00 13,600.00 6. Total Work Completed 268,582.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 268,582.00 68,830.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,830.00