Dept. of Trans. PROGRESS Serial No. Contract No. 25-057-14-17 07-4V3004 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 67% Location: Federal Project: 07-LA-5-8.2/8.2 NONE Progress payment No. 003 Payment period ending: 02-20-25 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 300,896.51 100,341.83 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 300,896.51 100,341.83 5. Mobilization 9,110.00 0.00 6. Total Work Completed 310,006.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 310,006.51 100,341.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,341.83